Work Progress
March 2025
The latest progress update focuses on the commencement of Trial Shaft work. We are collaborating with CMZ to prepare the drill pad area and stage the necessary tools and equipment. CMZ has already completed partial drilling to facilitate the installation of the casings. Concrete placement for the trial shaft is scheduled for Wednesday, 2/26/25.